Hanoi Department of Transport has just submitted to Hanoi People’s Committee the approval of constructing intersections in order to reduce traffic jam in Hanoi in the period 2010 – 2015.
O Cho Dua intersection will be constructed synchronously with a ring road from O Cho Dua – Cat Linh road– La Thanh road
Put forward the construction synchronously of the intersection (near Daewoo hotel) with the high line, from the ring road 1 – Lang road. Only for the intersection in the II ring road, Buoi intersection, Cau Giay constructs synchronously with ring road 2, Buoi – Cau Giay intersection before 2015 (belong to Project of Development of traffic infrastructure in second period).
For the intersections in ring road 3 as below:
+ Thanh Xuan intersection
+ Lang – Hoa Lac interchange
+ Hoang Quoc Viet interchange
+ Interchange “69”
+ Phu Lo intersection It constructed synchronously with ring road 3, Linh Dam – Mai Dich and from Mai Dich – Noi Bai before 2015.